Home / Case studies / Zakriya Mosque, Wishaw

Opening a masonry building into a single clear prayer hall

Multiple ground floor walls were removed to create a single open prayer hall in a traditional masonry building, with one internal staircase taken out and blocked off to form a plant room.

Sector Faith & communityLocation Wishaw, North LanarkshirePeriod 2022
The brief

What the project needed.

A prayer hall wants to be one uninterrupted space, and the building was not built that way. It is traditional masonry with existing steel beams, localised masonry piers taking bearing and a precast concrete plank floor over. Taking out several ground floor walls at once means the load they were carrying has to go somewhere, and the piers picking it up were never sized for it.

Work carried out

  • Structural calculations for removal of multiple ground floor walls
  • Design of supporting beams and framed openings
  • Bearing design onto localised masonry piers
  • Load take-down through the precast concrete plank floor
  • Racking and stability checks following staircase removal
  • Wind, dead and imposed loading assessment
  • Plant room formation at ground floor level
  • Calculation pack issued for building warrant
The engineering

What zakriya mosque, wishaw actually involves.

The load path was the whole job. Removing several walls in one operation changes how the floor above spans and concentrates what used to be distributed line loads onto a small number of new bearing points. Each one was designed rather than assumed, because a masonry pier that looks generous can still be the thing that governs once the load arriving at it has doubled.

The existing construction made that harder rather than easier. Traditional masonry with steel already built into it, on localised piers, under precast concrete planks, is a structure whose load paths are partly historic and not always where the drawings suggest. Sizes were taken from a site survey rather than from record information, and the pack states plainly that the contractor must check and measure before work starts.

One internal staircase was removed and blocked off to form a room, and a plant room formed at ground floor in the space it left. Removing a staircase takes out a stiff element as well as a circulation route, so racking checks were run as part of the pack rather than left as an assumption.

Fire protection was set at a minimum of 60 minutes for all elements, which for a building of public assembly is the point at which the structural design and the fire strategy stop being separate conversations.

Project record

Zakriya Mosque, Wishaw

Structural calculation pack covering loadings, superstructure, substructure and ancillaries, stair design and stability, with analysis output, issued at warrant stage.

Not sure what you need?Send us your drawings, or just a photograph of the wall. We will tell you what is required and what it costs before you commit to anything.
Start a project

Tell us what you are building.

£5m PI insuredEurocode basedChecked and signed

Send the drawings or describe the project. We confirm scope, deliverables and a realistic timescale.

Start a project