Digging out or lowering a basement means removing ground from under the walls that hold your house up, so the work is as much about sequence and temporary support as it is about the finished structure. We prepare the calculations and drawings that make it safe and satisfy Building Control, for clients across the UK.

How we work

Why is a basement conversion more involved than other projects?

You are removing ground from under the walls that hold your house up, so the work depends on a controlled sequence of underpinning and temporary support. The finished structure also has to retain soil and resist water, which makes it the most demanding domestic structural job.

In detail

Underpinning and lowering the ground

A basement conversion usually means lowering the floor level below the existing foundations, which cannot be done in one go without the walls losing their support. Underpinning extends the foundations downward in a controlled sequence of short bays, each dug out, cast and allowed to gain strength before the next is started, so the wall is never left unsupported over a long length. Getting the bay sequence and the hit-and-miss pattern right is the core of a safe basement job, and it is designed, not improvised on site.

We design the underpinning bays, their reinforcement and the sequence they are built in, and we check the ground and groundwater conditions that decide how deep and how wide each pin has to be. The new underpins become the retaining structure that holds back the soil around the lowered basement, so they are designed for the lateral earth pressures and any surcharge from the house and the neighbours as well as the vertical load they already carried.

Retaining the ground and keeping water out

Once the floor is lowered, the walls around the basement are retaining a full height of soil, and soil pushes sideways. We design the retaining walls for the lateral earth pressures set out in BS EN 1997-1 and its UK National Annex, including any surcharge from foundations, vehicles or a neighbour's building close to the boundary. The wall, its base and the way it connects to the new floor slab all have to resist that push without sliding, overturning or cracking.

Water is the other half of a basement. Below ground the structure sits in soil that can hold water, so the slab and walls are designed to resist water pressure and are combined with a waterproofing system, whether that is a waterproof concrete box, an external membrane or an internal drained cavity to BS 8102. We design the structure so the waterproofing has a sound backing, because a basement that is structurally fine but wet is not a usable room.

Neighbours, sequence and Building Control

Basement work almost always affects the party walls and the neighbours, because you are excavating below the level of adjoining foundations. We set out the loadings, depths and the excavation sequence a party wall surveyor needs, and design the temporary support that keeps both your house and the neighbour's stable while the permanent structure is built. The sequence of works is part of the design, not an afterthought, because the order the bays are dug and cast is what keeps everything standing.

The calculations are prepared to the Eurocodes, the relevant UK National Annex and Approved Document A, and cover the underpinning, the retaining walls, the slab, the waterproofing interface and the temporary works as one package. Because a basement is the most involved domestic structural project, we coordinate closely with your architect and contractor so the design, the sequence and the site work all line up, for clients across the UK.

Engineering considerations

What we check.

The points our calculations resolve for a project like this.

Not sure what you need?Send us your drawings, or just a photograph of the wall. We will tell you what is required and what it costs before you commit to anything.
Process

From enquiry to sign-off.

1

Enquiry

Send drawings or describe the problem. We confirm the scope, the deliverables and a target timescale.

2

Information

We agree the survey, drawings or data we need and any site access required.

3

Engineering

Design, calculation or assessment to the relevant Eurocodes and UK National Annex.

4

Issue

A clear, defensible report or set of calculations, with assumptions and limitations stated.

Questions

Common questions

Why is a basement conversion more involved than other projects?

You are removing ground from under the walls that hold your house up, so the work depends on a controlled sequence of underpinning and temporary support. The finished structure also has to retain soil and resist water, which makes it the most demanding domestic structural job.

How much does basement and underpinning design cost?

A single fixed fee covers the calculations and drawings, agreed before we begin. The fee reflects the depth of the dig, the length of underpinning, the retaining and waterproofing design and the temporary works, which vary a lot between projects.

What is underpinning and why is it done in bays?

Underpinning extends the existing foundations deeper so the floor can be lowered. It is done in short bays in a hit-and-miss sequence so the wall is never unsupported over a long length, with each bay cast and gaining strength before the next is dug.

Will a basement stay dry?

Only if the structure and waterproofing are designed together. We design the slab and walls to resist water pressure and provide a sound backing for a waterproofing system to BS 8102, whether that is waterproof concrete, an external membrane or an internal drained cavity.

How are the neighbours affected?

Basement work excavates below adjoining foundations, so the Party Wall etc. Act almost always applies. We provide the loadings, depths and sequence your surveyor needs and design the temporary support that keeps both properties stable during the works.

Start a project

Tell us what you are building.

£5m PI insuredEurocode basedChecked and signed

Send the drawings or describe the project. We confirm scope, deliverables and a realistic timescale.

Start a project